Raj Tools & Stamping Pvt. Ltd.

Operational Excellence & QMS Transformation

Improving productivity, audit readiness, and organizational discipline through structured QMS interventions — culminating in ZED Silver Certification.

Why They Teamed Up

Key challenges identified

Manpower utilization
Limited data-based decision making
Audit preparedness
5S and workplace discipline
Hidden productivity losses
Continuous improvement culture

Diagnostic Phase

Observations

Manpower was not optimally deployed.

Daily work was not consistently recorded.

5S and Safety awareness needed strengthening.

Data was available, but was not being used well for decisions.

Time losses and non-value-added activities were not visible.

Audit preparedness was below desired level.

Methodology

Approach adopted to improve performance

1. Shopfloor Study & Process Walkthrough2. Gap Analysis3. Manpower Utilization Review4. Time Loss Identification5. 5S and Safety Strengthening6. Daily Work Recording & Data Collection7. KPI Reviews8. Documentation Systems9. Productivity Improvement10. Audit Readiness11. ZED Certification

The Work

Interventions & outcomes

Workforce Optimization & Productivity Improvement

Actions Taken

  • Department-wise manpower review
  • Identification of excess manpower
  • Workload balancing

Outcomes

  • Improved manpower utilization
  • Better productivity
  • Reduced inefficiencies

Key Insights

  • Staff workforce was optimized by 12%.
  • Critical employees retained through job rotation.
  • Talent redeployed where higher value could be generated.
  • Productivity improved despite lower manpower.

Strengthening Shopfloor Discipline through 5S & Safety

Actions Taken

  • 5S awareness sessions conducted
  • Safety awareness trainings
  • Regular workplace inspections

Outcomes

  • Improved workplace organization
  • Better safety awareness among employees
  • Increased ownership of work areas

Key Insights

  • 5S and Safety became part of daily working culture rather than periodic activities.
  • Regular 5S and Safety audits are now conducted, including inspection of first-aid boxes and firefighting equipment.

Creating a Data-Driven Decision-Making Culture

Actions Taken

  • Daily work recording system introduced
  • Departmental performance data collected
  • Regular MIS reviews
  • Teams trained to analyse and interpret data

Outcomes

  • Better visibility of operational performance
  • Increased accountability
  • Faster identification of issues
  • More informed decision-making

Key Insights

  • Teams shifted from assumption-based decisions to fact-based decisions.
  • Data became a management tool rather than just a record-keeping exercise.
The actual Daily Planner format (Doc No. RTSPL/HR/20) introduced at Raj Tools & Stamping as part of the daily work recording system.

The actual Daily Planner format (Doc No. RTSPL/HR/20) introduced at Raj Tools & Stamping as part of the daily work recording system.

Identifying & Eliminating Hidden Productivity Losses

Actions Taken

  • Daily activity analysis
  • Time-loss tracking
  • Department-level reviews
  • Identification of non-value-added activities

Outcomes

  • Better utilization of working hours
  • Reduced wasted efforts
  • Increased focus on productive work
  • Improved operational efficiency

Key Insights

  • Employees began tracking daily planned vs. actual activities.
  • Daily tasks were assigned estimated completion times to improve accountability and planning accuracy.
  • End-of-day reviews compared planned activities against actual execution and time consumed.

Strengthening Audit Readiness

Actions Taken

  • Documentation discipline strengthened
  • Daily records maintained
  • Periodic internal reviews conducted

Outcomes

  • Faster document retrieval
  • Better compliance visibility
  • Reduced dependence on individuals
  • Increased confidence during audits

Key Insights

  • The organization evolved from being audit-dependent on a few individuals to being increasingly system-driven and audit ready.
  • Standard documents and formats were prepared, including a standard SOP document and presentation templates.

Achieving ZED Silver Certification

Successfully achieved ZED Silver Certification during the engagement period. Certification validated improvements in quality systems, workplace discipline, process management, and organizational maturity. The certification was not the objective; it was the outcome of systematic operational improvements implemented across the organization.

ZED Silver certificate no. 10072025_246813, issued 10 July 2025 by the Ministry of MSME under the MSME Sustainable (ZED) Certification Scheme.

ZED Silver certificate no. 10072025_246813, issued 10 July 2025 by the Ministry of MSME under the MSME Sustainable (ZED) Certification Scheme.

Overall Business Impact

From reactive to disciplined and data-driven.

12%

Workforce Optimization

Improved

Productivity

Institutionalized

5S & Safety Culture

Established

Data-Driven Decision Making

Implemented

Time-Loss Visibility

Significantly Improved

Audit Readiness

Achieved

ZED Silver Certification

Strengthened

Organizational Discipline